Port Blair, June 28: Power supply will remain suspended at the following area on 30.6.2018 (Saturday) from 0730 Hrs. to 1500 Hrs. in connection with rectification of underground power cable of 33 KV VOR tie line near CPAO Office, Port Blair.
Date
Area affected Timing
From To
30.06.2018 (Saturday) Vidhyut Bhawan, Electricity HQ Office, PBMC Auditorium, APWD CE Office, Secretariat, Court Complex, PAO, Raj Niwas & Gandhi Park, Shadipur, South Point, Mazaar Pahad, Machi Line, RGT Road, Govt. Press and JNRM College, part of Dollygunj area, DBRAIT, Loknath Colony, Royal Colony Dollygunj, FCI and Rajiv Nagar Housing Colony 0730 Hrs. 1500 Hrs.
In addition to above, one hour load shedding will also be carried out on 30.06.2018 from 0730 Hrs. to 1130 Hrs. in the following area as per schedule given below for maintenance and servicing of OLTC of 6.3 MVA power transformers at Garacharama Sub-Station.
Date Area affected Timing
From To
30.06.2018 Part of Bhatu Basti, Attom Pahar, Dollygunj complete and part of Old Pahargaon 0730 Hrs. 0830 Hrs.
Old Pahargaon, part of Dollygunj village, School Line, Lamba Line and Ranchi Basti. 0830 Hrs. 0930 Hrs.
Pathergudda, Bhatu Basti, part of Prothrapur village and New Pahargaon. 0930 Hrs. 1030 Hrs.
Garacharama complete and part of Bhatu Basti. 1030 Hrs. 1130 Hrs.
The above mentioned work will be carried out subject to weather condition and time mentioned is tentative which may change subject to completion of work. The inconvenience caused is regretted.