Port Blair, May 25: Due to breakdown of 5 MW DG set at M/s. Suryachakara Power Plant, Bambooflat, there is shortage in power generation and the ongoing load shedding will continue in Port Blair and South Andaman area during evening peak hours from 5.45 PM to 10.45 PM for 01 Hours on every alternate day as per the following schedule. This schedule is being in effect from today (25.5.2017) onwards till next fortnight. The evening hours load schedule is tentative and may vary in view of public meetings, important social functions or other emergency reasons.
Date Time Area affected
25.5. 17 05.45 PM To 06.45 PM Part of Sippighat, Chouldari Lal Pahar, Tsunami Shelter, Mithakhari, Namunaghar, Dunduspoint, Hathi Tappu, Buniyadabad, AIR, DDK Colony, part of Delanipur, part of Prem Nagar, Coast Guard Enclave, Coast Guard HQ, Coast Guard Jetty, Panipath Road, Fortress Head Quarter, STS Workshop, BSNL Bhawan, Model School Area, Fire Brigade, ANIIDCO Bhawan area, Girls School, CCS Aberdeen Bazaar area, Supply Line complete, Netaji Stadium area, Electricity Bazaar site office, Jama Masjid, Netaji Club and part of Gurudwara Lane.
06.45 PM To 07.45 PM Shadipur, South Point, Mazaar Pahad, Machi Line, RGT Road, Govt. Press, JNRM College, Mohanpura, Babu Lane, Aberdeen Bazaar from Ratnam Market to Taxi Stand, Aberdeen Thana and part of Gurudwara Lane.
07.45 PM To 08.45 PM CARI, AKT Miniplex, Bird Line, Calicut, Kamaraj Nagar, Beodnabad, Rangachang, Burmanallah & Chidiyatapu, Part of Gurudwara Lane, Bengali Club, Biggi Lane, Anthropological Museum, Middle Point, Link Road, VIP Road, Police Line, part of Junglighat
08.45 PM To 09.45 PM Garacharama Sub Station, Japan Nallah, Austinabad, Prothrapur, Carbyn’s Cove, Brichgunj, Brookshabad, part of Chakkargoan, Dairy Farm Junction, CPWD Complex, Lamba Line, Ranchi Tekery, School Line complete and part of Minnie Bay.
09.45PM To 10.45 PM Part of Dollygunj, part of Pahargaon, ICMR Colony area, part of School Line, Water Treatment Plant area at Lamba Lane, Mathura, Bridavan, Ferargunj to Jirkatang, Stewart Gunj, Kanyapuram, Wimberlygunj, Shoal Bay and Hopetown.
26.5. 17 05.45 PM To 06.45 PM Bhatu Basti complete, Laxmi Motor Area, Pathergudda, Setlite Colony, New Pahargaon, Marine Hill, Dugnabad complete, Round Basti, Netaji Club area, Rajasthan Mandir, ALWH Colony, Hawaghar Jn., Dudh Line, Nayagaon, Bargat Line, GPRA Colony & Carbyn’s Jn.
06.45 PM To 07.45 PM Part of Garacharama, Dollygunj, Attompahar, Old Pahargaon, ICMR Colony area, part of Minnie Bay, BSNL Telephone Exchange, Prem Nagar, Goalghar, Carmel School area, KV-I area, Murdakhari area and Bambooflat.
07.45 PM To 08.45 PM Sippighat, Teylarabad, Bimblitan, Manjeri, Guptapara, Manglutan, Wandoor, Chouldari Tushnabad, Port Mount, Tirur, Templemyo, Ograbranj, Haddo, Haddo Warf, Foreshore Road, upto Civil Aviation Delanipur, Shristy Nagar, Atlanta Point, Cellular Jail, G.B.Pant and Police HQ, Marina Park and Aberdeen Bazaar site office area
08.45 PM To 09.45 PM Part of Junglighat, Vijay Baugh, Dairy Farm complete, Agency House, Garacharama complete & 5 MW Solar Power Plant area.
09.45PM To 10.45 PM Chatham Mill, Chatham Wharf, IOC, MES Power Hous and Light House, Phoenix Bay, Fisheries Jetty area, Anarkali, Delanipur, Quarry Hill, Phongy Kyaung, Foreshore Road, Megapode, Teal House and Horticulture Road
The schedule will be repeated every alternate day till next fortnight.
The inconvenience caused is deeply regretted and the consumers are requested to bear with the situation.