Sri Vijaya Puram, Feb. 10:General public/consumers and Government Departments have been informed that the power supply will remain suspended on 11/02/2026 in connection to carry the inter connection work at Wimberlygunj and ABS setting work in 4 pole structure at Ferrargunj and pole shifting at Bangla Pahad under South Andaman Division. Details are as given below –
| Date
|
Timing
|
Feeder
|
Affected Area
|
|
| From
|
To
|
|||
| 11/02/2026
|
08.00 am
|
02.00pm
|
SBFG Feeder
|
B/Flat substation to Tanki Pahad, Tanki Pahad to W/ gunj, Shoalbay complete, W/gunj to Ferrargunj, Jirkatang complete.
|
| PV Feeder
|
Shore Point, Govinda Puram to W/ Gunj & Lamba Pahad & Kanya Puram.
|
|||
The above works will be carried out subject to weather condition and if the work completes earlier, the feeder will be charged accordingly.